A9 LUNCARTY TO PASS OF BIRNAM

Project Description

In February 2019 we started works on phase one of the A9 dualling works for Balfour Beatty (we also carried out phase one of the A9 dualling works for Wills/John Paul as shown in previous contracts section).  Within this phase of the works we will carry out temporary fencing, permanent fencing, permanent safety barrier, parapets and pedestrian guardrail works.

We are undertaking the following works within this contract:

Temporary Fencing – Approximately 12,000m (plus gates)
Permanent Fencing – Approximately 40,000m (plus gates)
Parapet Works – Approximately 1,000m (over 5 structures)
Permanent Barrier Works – Approximately 20,000m (plus terminals and transitions)
Pedestrian Guardrail Works – Approximately 200m

The works also include a bespoke handrail and barrier installation which was design and installed successfully by our team (see pictures below).

These works are ongoing at present with a completion date of summer 2021.

Project Info

  • Location
    A9 Luncarty to Bankfoot
  • Client
    Balfour Beatty
  • Date
    Commenced Feb 2019, Completed in August 2021.

Project Gallery

More Recent Contracts